Prototype Delivery Plan

Rooftop Garden

An interactive 3D prototype of a movable rooftop hydroponic system — plus the AI tooling that runs nutrient & plant management behind it. This is the plan to deliver it, and the program you'd run.

7 milestones 7 work tracks ~79 build-days of scope 2 execution owners + PM

Prepared for Mia  ·  Program lead role  ·  Sponsor: Adam

The ask

You'd run the program end to end

The design is fully specified — 17 source documents cover the geometry, plant rendering, mechanics, irrigation, and detail views. What it needs now is someone to drive it to a shipped prototype: sequence the work, bring on and manage a build engineer, hold the cadence, own the handshake between the build and Adam's AI tooling, run quality gates, and coordinate launch. That program-management role is what this plan maps — your workstreams, milestone by milestone.

Delivery model

Who does what

Three roles. You drive; two owners execute. Your first job is to make the two execution seats productive and keep them in sync.

Drives the program

Program Manager

Mia (Resource #2)
  • Owns delivery of the prototype
  • Plan, cadence, sequencing, unblocking
  • Sources & manages the build engineer
  • Quality gates & milestone sign-off
  • Risk, change, and launch coordination
Executes the build

Build Engineer

To be sourced & managed by PM
  • Three.js prototype (Tracks A–E, G)
  • Geometry, plants, mechanics, irrigation
  • Detail modals & UI, landing page
  • Reports into the PM cadence
Executes AI tooling

AI Tooling Engineer

Adam (sponsor + Track F)
  • Nutrient & plant-management software
  • Data schema, dosing logic, harvest model
  • API feeding the live dashboard
  • Dependency the PM coordinates
Roadmap

Seven milestones

Indicative timeline assumes one build engineer working the prototype tracks in sequence, with Adam's AI tooling running in parallel from mid-program. Your focus shifts at each stage.

Weeks 1–2Setup + M1

M1PoC Validated

Two-track artifact proves chain articulation around the eave and click-to-detail interaction.
Your focus: stand up governance, source the build engineer, confirm the PoC baseline.
Weeks 3–5M2

M2Five-Track System

Scale to five crops, reservoirs, plumbing, exact 14-cube deploy, master toggle.
Your focus: lock the early design decisions (below) to prevent rework; hold first demo review.
Weeks 5–7M3

M3Plant Fidelity Locked

Billboard-texture plants at mature size and density with tuned per-crop palettes.
Your focus: enforce the billboard technique decision; sign off visual quality.
Weeks 7–10M4

M4Mechanical Detail Complete

Axles & bearings, free-hanging deployment below the eave, and the clickable solar-housing interior modal.
Your focus: eave approach is locked to free-hang — steer effort into axle/bearing detail and the housing interior, not another rail redesign.
Weeks 9–12M5

M5Integrated UI & Dashboards

Deploy sliders, unified reservoir, clickable tablet dashboard, 60fps performance pass.
Your focus: broker the data-contract handshake with Adam; run QA against the acceptance checklist.
Weeks 11–15M6 (parallel)

M6AI Tooling MVP

Live EC/pH, water-level, dosing and harvest data served via API into the tablet — no hardcoded values.
Your focus: keep Adam unblocked; coordinate integration between tooling and dashboard.
Weeks 15–16M7

M7Launch

Landing page deployed, playground linked, responsive + accessibility QA passed.
Your focus: coordinate launch, final QA sign-off, and handoff.
Your responsibilities

The program-management work

Every task you'll own to make the prototype happen, grouped into seven workstreams that run across the whole program.

1

Governance & Planning

  • Define scope, success criteria, and the definition of "done" per milestone
  • Own and maintain this roadmap and the backlog
  • Set up the repo, issue tracking, and working cadence (standups + milestone demos)
  • Build the stakeholder map and communications rhythm
2

Resourcing

  • Scope the build-engineer role and source the right person
  • Onboard the engineer to the 17 source docs and the design intent
  • Manage hours/budget and capacity across the two execution seats
  • Coordinate Adam as the AI-tooling dependency owner
3

Execution Management

  • Drive M1–M7 to completion; groom and prioritize the backlog
  • Run build cadence and demo reviews at each milestone gate
  • Track progress vs. plan; surface and remove blockers
  • Manage schedule and dependencies between tracks
4

Technical Coordination

  • Facilitate the early design decisions that prevent rework
  • Own the data-contract handshake between the dashboard and Adam's API
  • Keep build and AI tooling aligned on the integration point (the tablet)
  • Escalate technical trade-offs for a sponsor decision when needed
5

Quality

  • Coordinate QA against the 16-item acceptance checklist
  • Verify milestone exit criteria before advancing
  • Own visual-fidelity and performance sign-off (60fps target)
  • Track defects to closure
6

Risk & Change

  • Maintain the risk register and drive mitigations
  • Pre-empt the known rework threads (rails/eave, nozzles, plants)
  • Manage scope changes and their schedule impact
  • Protect against key-person risk on the AI track
7

Launch

  • Coordinate the landing page, preview capture, and deploy
  • Own responsive + WCAG-AA acceptance for the public page
  • Run the launch checklist and go/no-go
  • Handoff and retrospective
Ownership map

Tracks & ownership

You are accountable for all seven tracks landing. These are the doers you'll coordinate on each.

TrackWhat it deliversExecutesPM role
A · Foundation & GeometryScene, house, chain path, raise/lower, deploy slidersBuild EngineerAccountable · sequence & unblock
B · Plant RenderingBillboard plants, textures, lushness, maturity sliderBuild EngineerAccountable · quality sign-off
C · Rails & MechanicsBrackets, slope rails, axles/bearings, free-hang deploy (opt. bottom guide)Build EngineerAccountable · eave decision locked
D · IrrigationReservoirs, hoses, unified tank, drip nozzlesBuild EngineerAccountable · decision owner
E · Detail Modals & UICross-section modal, controls, tablet dashboard, perfBuild EngineerAccountable · integration point
F · AI Nutrient/Plant ToolingSchema, dosing, harvest model, API, integrationAdamCoordinates dependency & handshake
G · Landing Page & LaunchPublic page, preview, deploy, QABuild EngineerAccountable · launch owner
Program Manager (you) — accountable across all Build Engineer — prototype execution Adam — AI tooling
Steer early

Decisions that prevent rework

The source prompts show the design changing its mind mid-build. One is now locked (eave mechanics → free-hang); locking the rest before M2–M4 is the single biggest thing you can do to protect the schedule.

Eave mechanics — DECIDED: free-hang

Locked: the site is calm, so the deployed chain hangs freely below the eave. No wall rails, no cantilever cage — both dropped as unnecessary weight, cost, and eave load. Optional light bottom-alignment guide only if the vision system later needs tighter cube positioning. Not to be reopened.

Drip-nozzle location moves three times (ridge → fixed → into housing)

Call: route nozzles inside the housing from the start, before plumbing is built.

Procedural plant geometry is a dead end

Call: use the billboard-texture technique immediately — don't repeat the failed geometry passes.

AI tooling needs a stable data contract

Call: lock the dashboard data schema (Adam's Track F1) before the tablet dashboard is finalized, so integration is clean.

Where you'd start

First 30 days

A concrete on-ramp so the program has momentum from week one.

  1. Absorb the design. Work through the 17 source docs and the existing PoC; confirm what's already validated (chain articulation + click-to-detail).
  2. Stand up governance. Set up the repo, issue board, milestone gates, and a weekly demo cadence.
  3. Source the build engineer. Scope the role, run the search, and onboard them to the design intent.
  4. Lock the remaining rework-prevention decisions with Adam before build scales past M1 — eave mechanics is already settled to free-hang.
  5. Align the AI handshake. Agree the dashboard data schema with Adam so Tracks E and F converge cleanly.
  6. Publish the plan. Put this roadmap in the repo as the shared source of truth and start tracking against it.